Suraj Park View
Completion due Dec 2031Ward Gnorth, Maharashtra 400028 |Promoter: Suraj Estate Developers Ltd
Project summary
As registered with MahaRERA
- RERA registrations
- 2
- Phases
- 2
Location
Coordinates as published by MahaRERA
Also registered as
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 31 Dec 2026
P51900047891- Registered
- 1 Dec 2022
- Promised
- 31 Dec 2026
Completion promised for 31 Dec 2031
PR1170002500887- Registered
- 22 Sep 2025
- Promised
- 31 Dec 2031
2 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51900047891 | 1 Dec 2022 | 31 Dec 2026 | — | Suraj Estate Developers Ltd | Project page |
| PR1170002500887 | 22 Sep 2025 | 31 Dec 2031 | — | Suraj Estate Developers Ltd | Project page |
Documents
2 documents held by Deedo
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Mumbai City
Survey, CTS, gat or plot numbers
Source: registration certificates, as stated there.