Bayview

Completion due Dec 2027

Ward E, Maharashtra 400010 |Promoter: Kapil Constructions

16 Aug 2017Registered with MahaRERAFirst of 2 registrations
31 Dec 2027Promised completionLatest across registrations
30 Mar 2023Revised completion1 of 2 registrations pushed back, by up to 1 year
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA

RERA registrations
2
Phases
2

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.97022, 72.84166
Bayview is at latitude 18.97022, longitude 72.84166.

Also registered as

Bayview Phase-II
MahaRERA's project page hasn't been imported for this project yet.

Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 1 year

P51900006866

The latest completion date on record passed 3 years and 7 months ago.

Registered
16 Aug 2017
Promised
30 Mar 2022
Revised
30 Mar 2023

Completion promised for 31 Dec 2027

P51900048634
Registered
10 Jan 2023
Promised
31 Dec 2027

2 RERA registrations

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5190000686616 Aug 201730 Mar 202230 Mar 2023Kapil ConstructionsProject page
P5190004863410 Jan 202331 Dec 2027—Kapil ConstructionsProject page

Documents

3 documents held by Deedo

Registration certificates

  • Registration certificateP51900006866 · 9 Sep 2021ViewSource
  • Registration certificateP51900048634 · 10 Jan 2023ViewSource

Extension certificate

  • Extension certificateP51900006866 · 30 Mar 2022ViewSource

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

Survey, CTS, gat or plot numbers

318319320321322325327