Avenue 15
Certificate SignedVimannagar, Mumbai City 400015 |Promoter: Ramesh Barrel Supplying Co
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Buildings
- 1
- Unit types
- 1.5 Bhk, 1BHK, 1RK, 2BHK, Commercial127 units in all
- Address
- Plot No. 5C/172, Sitaram Palturam Murai Marg, SewriPIN 400015
- Designated bank account
- 109
- Developed in phases
- No
Location
Coordinates as published by MahaRERA
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 4 months
- Registered
- 14 Dec 2021
- Promised
- 30 Sep 2026
- Revised
- 30 Jan 2027
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51900032165 | 14 Dec 2021 | 30 Sep 2026 | 30 Jan 2027 | Ramesh Barrel Supplying Co | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Avenue 15 | 23 | 127 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
20 of 127 units booked (16%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1.5 Bhk | 49.39 sq m · 532 sq ft | 22 | 3 |
| 1BHK | 38.7 sq m · 417 sq ft | 21 | 3 |
| 1BHK | 40.05 sq m · 431 sq ft | 21 | 2 |
| 1BHK | 40.35 sq m · 434 sq ft | 20 | 5 |
| 1BHK | 40.75 sq m · 439 sq ft | 20 | 3 |
| 1RK | 24.49 sq m · 264 sq ft | 1 | 0 |
| 2BHK | 60.68 sq m · 653 sq ft | 21 | 4 |
| Commercial | 80.92 sq m · 871 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
1 document held by Deedo, 100 filings listed on MahaRERA's project page
Finance
- PAN CardPANCARD RAMESH.pdf · uploaded 25 Oct 2021Source
Legal
Migrated
- 1 PAN CardPANCARD RAMESH.pdf · uploaded 25 Oct 2021Source
- 1 Details of encumbrancesEncumbrance avenue.pdf · uploaded 25 Oct 2021Source
- 1 Declaration in FORM BForm B Avenue.pdf · uploaded 25 Oct 2021Source
- 1 Proforma of Allotment letterRevised Agreement For Sale - Avenue 15 Clean.pdf · uploaded 17 Nov 2021Source
Show all 101 documentsShow fewer documents
Migrated
- 2 Proforma of Allotment letterLetter of Allotment - 12th Nov Avenue 15 clean.pdf · uploaded 17 Nov 2021Source
- 1 Copy of Layout Approval (in case of layout)Plan Scrutiny amend 2_1-1.pdf · uploaded 18 Nov 2021Source
- 1 Building Plan Approval / NA Order for plotted developmentdownload.pdf · uploaded 18 Nov 2021Source
- 2 Building Plan Approval / NA Order for plotted developmentPLAN RAMESH_compressed_compressed_2-2.pdf · uploaded 18 Nov 2021Source
- 3 Building Plan Approval / NA Order for plotted developmentPLAN RAMESH_compressed_compressed_3-3.pdf · uploaded 18 Nov 2021Source
- 4 Building Plan Approval / NA Order for plotted developmentPLAN RAMESH_compressed_compressed_4-end_11zon.pdf · uploaded 18 Nov 2021Source
- 1 Commencement Certificates / NA Order for plotted developmentFurther Cc.pdf · uploaded 18 Nov 2021Source
- 1 Declaration about Commencement CertificateFormat D Rbsco (1).pdf · uploaded 19 Nov 2021Source
- 1 Copy of the legal title reportRERA TITLE NEW HARIYANI-1-3.pdf · uploaded 2 Dec 2021Source
- 1 CERSAI detailsCERSAI_Search_Report Ramesh Barrel.pdf · uploaded 2 Dec 2021Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architects rera certificate 1.pdf · uploaded 4 Dec 2021Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 Avenue 15.pdf · uploaded 4 Dec 2021Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Certificate 221.pdf · uploaded 4 Dec 2021Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Avenue 15 Form 2- 31st March 2022_compressed.pdf · uploaded 11 May 2022Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Ramesh Barrel Supplying Co- 31st March 2022_compressed.pdf · uploaded 11 May 2022Source
- 2 Commencement Certificates / NA Order for plotted developmentLatest CC.pdf · uploaded 1 Sep 2022Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Avenue 15 Form 2- 30th June 2022.pdf · uploaded 1 Sep 2022Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Avenue 15 June 2022.pdf · uploaded 1 Sep 2022Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Avenue 15- Form 1.pdf · uploaded 13 Sep 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 of Avenue 15 FY 2021-22.pdf · uploaded 1 Oct 2022Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Avenue 15 (September 2022).pdf · uploaded 11 Nov 2022Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Avenue 30 September 2022_compressed.pdf · uploaded 11 Nov 2022Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5- Avenue 15 (REVISED).pdf · uploaded 12 Nov 2022Source
- 1 Disclosure of sold/ booked inventoryAVENUE 15 CIRCULAR 29.pdf · uploaded 26 Nov 2022Source
- 2 Declaration about Commencement CertificateFormat D- Avenue 15.pdf · uploaded 19 Jan 2023Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Avenue 15 as on Decmeber 2022.pdf · uploaded 6 Feb 2023Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3- Avenue 15 as on December 2022.pdf · uploaded 6 Feb 2023Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 21 Apr 2023Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)New format- Final Form 3 Avenue 31 March 2023.pdf · uploaded 21 Apr 2023Source
- 2 Disclosure of sold/ booked inventoryAVENUE 15.pdf · uploaded 25 Apr 2023Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Avenue 15 as on June 2023.pdf · uploaded 20 Jul 2023Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3- Avenue 15 as on 30-06-2023.pdf · uploaded 20 Jul 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)New Format Form 5 Avenue 15 FY22-23.pdf · uploaded 6 Sep 2023Source
- 3 Disclosure of sold/ booked inventoryCircular 29 as on 30-06-23.pdf · uploaded 7 Sep 2023Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Avenue 15 as on 30-09-2023.pdf · uploaded 17 Oct 2023Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Avenue 15 as on September 2023.pdf · uploaded 20 Oct 2023Source
- 4 Disclosure of sold/ booked inventoryCircular 29 as on Sep 2023.pdf · uploaded 25 Nov 2023Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Avenue 15 as on Dec 2023.pdf · uploaded 16 Jan 2024Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Avenue 15 31-12-2023.pdf · uploaded 16 Jan 2024Source
- 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Avenue 15 as on March 2024.pdf · uploaded 20 Apr 2024Source
- 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Avenue 15 as on 31st March 2024.pdf · uploaded 20 Apr 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Avenue 15 as on March 2024.pdf · uploaded 25 Apr 2024Source
- 5 Disclosure of sold/ booked inventoryCircular 29 - Avenue 15 as on March 2024.pdf · uploaded 4 Jun 2024Source
- 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Avenue 15 as on June 2024.pdf · uploaded 18 Jul 2024Source
- 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Avenue 15 as on 30-06-2024.pdf · uploaded 18 Jul 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Avenue 15 as on 30-09-2024.pdf · uploaded 19 Oct 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Avenue 15 as on 30-09-2024.pdf · uploaded 19 Oct 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Avenue 15 as on Sep 2024.pdf · uploaded 29 Oct 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 - Avenue 15 for FY 2023-24.pdf · uploaded 8 Nov 2024Source
- 1 Disclosure of sold/ booked inventoryCircular 29 Avenue 15 as on Sep 2024.pdf · uploaded 30 Nov 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Avenue 15 as on Dec 2024.pdf · uploaded 15 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Avenue 15 as on Dec 2024.pdf · uploaded 15 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Avenue 15 as on Dec 2024.pdf · uploaded 27 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Avenue 15 as on March 2025.pdf · uploaded 20 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Avenue 15 as on March 2025.pdf · uploaded 20 Apr 2025Source
- Form 1Form 1 - Avenue 15 as on June 2025.pdf · uploaded 19 Jul 2025Source
- Form 2Form 2 - Avenue 15 as on June 2025.pdf · uploaded 19 Jul 2025Source
- Form 3Form 3 - Avenue 15 as on June 2025.pdf · uploaded 19 Jul 2025Source
- Disclosure of Sold and Booked InventoryCircular 29 - Avenue 15 as on June 2025.pdf · uploaded 19 Jul 2025Source
- Withdrawal Update Form 1Form 1 - Avenue 15 as on Sept 2025.pdf · uploaded 25 Oct 2025Source
- Withdrawal Update Form 2Form 2 - Avenue 15 as on Sept 2025.pdf · uploaded 25 Oct 2025Source
- Withdrawal Update Form 3Form 3 - Avenue 15 as on Sept 2025.pdf · uploaded 25 Oct 2025Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 2Form 2 - Avenue 15 as on Dec 2025.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 3Form 3 Avenue 15 as on 31-12-2025.pdf · uploaded 20 Jan 2026Source
- Form 5 (FY 2024-2025)Form 5 Avenue 15 FY 2024-25 (Working).pdf · uploaded 26 Feb 2026Source
- Withdrawal Update Form 1Form 1 Avenue 15 as on 31-03-2026.pdf · uploaded 12 Apr 2026Source
- Withdrawal Update Form 2Form 2 Avenue 15 as on 31-03-2026.pdf · uploaded 12 Apr 2026Source
- Withdrawal Update Form 3Form 3 Avenue 15 as on 31-03-2026.pdf · uploaded 12 Apr 2026Source
- Withdrawal Update Form 1Form 1 - Avenue 15 June 2026.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 2Form 2 - Avenue 15 June 2026.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 3Form 3 - Avenue 15 June 2026.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 1Form 1 - Avenue 15 June 2026.pdf · uploaded 2 Sep 2026Source
- Withdrawal Update Form 2Form 2 - Avenue 15 June 2026.pdf · uploaded 2 Sep 2026Source
- Withdrawal Update Form 3Form 3 - Avenue 15 June 2026.pdf · uploaded 2 Sep 2026Source
- Form 2A (FY 2021-2022)Form - 2A Avenue 15 on FY 2021-2022.pdf · uploaded 11 Sep 2026Source
- Form 2A (FY 2022-2023)Form - 2A Avenue 15 on FY 2022-2023.pdf · uploaded 11 Sep 2026Source
- Form 2A (FY 2023-2024)Form - 2A Avenue 15 on FY 2023-2024.pdf · uploaded 11 Sep 2026Source
- Form 2A (FY 2024-2025)Form - 2A Avenue 15 on FY 2024-2025.pdf · uploaded 11 Sep 2026Source
- Form 2A (FY 2025-2026)form 2A Avenue 15 on 2025-26.pdf · uploaded 15 Sep 2026Source
- Form 5 (FY 2025-2026)Avenue_15_Form5_2025-26_30-09-2026_14-33.pdf · uploaded 30 Sep 2026Source
Technical
- DocumentPlan Scrutiny amend 2_1-1.pdf · uploaded 18 Nov 2021Source
- Documentdownload.pdf · uploaded 18 Nov 2021Source
- DocumentPLAN RAMESH_compressed_compressed_2-2.pdf · uploaded 18 Nov 2021Source
- DocumentPLAN RAMESH_compressed_compressed_3-3.pdf · uploaded 18 Nov 2021Source
- DocumentPLAN RAMESH_compressed_compressed_4-end_11zon.pdf · uploaded 18 Nov 2021Source
Technical (Architect)
Technical (Engineer)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Vimannagar
Survey, CTS, gat or plot numbers
Boundaries
- North
- 5c-1 172
- South
- Sitaram Palturam Murai Marg
- East
- 2c 172
- West
- 18 M Wide Road
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Chartered accountant | Parth Gada | — |
| Engineer | Ajay Shukla | — |
Source: MahaRERA project page. Contact details are not shown.