Siddha Sky

Completion due Dec 2030

Mumbai City 400037 |Promoter: Sejal Shakti Realtors LLP

27 May 2019Registered with MahaRERAFirst of 2 registrations
30 May 2027Promised completionLatest across registrations
31 Dec 2030Revised completion1 of 2 registrations pushed back, by up to 3 years and 7 months
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA

RERA registrations
2
Phases
2

Also registered as

Siddha Sky Phase 4Siddha Sky Phase 1
MahaRERA's project page hasn't been imported for this project yet.

Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 3 years and 7 months

P51900021031
Registered
27 May 2019
Promised
30 May 2027
Revised
31 Dec 2030

Completion promised for 30 Jun 2026

P51900021027

The latest completion date on record passed 4 months ago.

Registered
27 May 2019
Promised
30 Jun 2026

2 RERA registrations

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5190002103127 May 201930 May 202731 Dec 2030Sejal Shakti Realtors LLPProject page
P5190002102727 May 201930 Jun 2026—Sejal Shakti Realtors LLPProject page

Documents

3 documents held by Deedo

Registration certificate

  • Registration certificateP51900021031 · 8 Sep 2021ViewSource

Extension certificates

  • Extension certificateP51900021031 · 21 May 2024ViewSource
  • Extension certificateP51900021027 · 14 Aug 2026ViewSource

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Mumbai City

Survey, CTS, gat or plot numbers

12 pt of sion division16 pt to 21 pt of salt pan division6 pt

Source: registration certificates, as stated there.

SourcesMahaRERA project search · registration certificatesMethodology