Matoshree Pride

Completion date passed

Mumbai City 400012 |Promoter: Matoshree Properties

6 Aug 2017Registered with MahaRERAFirst of 2 registrations
31 Dec 2018Promised completionLatest across registrations
31 Dec 2019Revised completion1 of 2 registrations pushed back, by up to 1 year
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA

RERA registrations
2
Phases
2

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.00415, 72.84718
Matoshree Pride is at latitude 19.00415, longitude 72.84718.

Also registered as

Matoshree Pride Building 1Matoshree Pride Building 2
MahaRERA's project page hasn't been imported for this project yet.

Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 1 year

P51900003736

The latest completion date on record passed 6 years and 10 months ago.

Registered
6 Aug 2017
Promised
31 Dec 2018
Revised
31 Dec 2019

Completion promised for 31 Dec 2018

P51900006687

The latest completion date on record passed 7 years and 10 months ago.

Registered
16 Aug 2017
Promised
31 Dec 2018

2 RERA registrations

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P519000037366 Aug 201731 Dec 201831 Dec 2019Matoshree PropertiesProject page
P5190000668716 Aug 201731 Dec 2018—Matoshree PropertiesProject page

Documents

3 documents held by Deedo

Registration certificates

  • Registration certificateP51900003736 · 6 Aug 2017ViewSource
  • Registration certificateP51900006687 · 16 Aug 2017ViewSource

Extension certificate

  • Extension certificateP51900003736 · 3 Jun 2019ViewSource

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Mumbai City

Survey, CTS, gat or plot numbers

660C S No 660

Source: registration certificates, as stated there.

SourcesMahaRERA project search · registration certificatesMethodology