364 Ews T/S Under Pmay At Jalna Dis Jalna

Lapsed

Jalna (M Cl), Jalna 431213 |Promoter: Aurangabad Housing And Area Development Board ( A Regional Unit Of Mhada)

Residential / Group HousingRERAP51400012018
1 Sep 2017Registered with MahaRERA
2 Jul 2019Promised completion
1 Jan 2021Revised completionPushed back 1 year and 6 months
25Buildings
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Lapsed
Buildings
25
Land area for this project
27,922 sq m (3,00,544 sq ft)
Permissible built-up area
20,585 sq m (2,21,572 sq ft)
Sanctioned built-up area
20,585 sq m (2,21,572 sq ft)
Recreational open space
5,962 sq m (64,172 sq ft)
Planning authority
Municipal Council, Jalna
Address
488/15, shiraswadi road, jalnaPIN 431213
Designated bank account
Bank Of Maharashtra
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.82973, 75.86311
364 Ews T/S Under Pmay At Jalna Dis Jalna is at latitude 19.82973, longitude 75.86311.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 1 year and 6 months

The latest completion date on record passed 5 years and 9 months ago.

Registered
1 Sep 2017
Promised
2 Jul 2019
Revised
1 Jan 2021

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P514000120181 Sep 20172 Jul 20191 Jan 2021Aurangabad Housing And Area Development Board ( A Regional Unit Of Mhada)Project page

25 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Bldg No 12—
Bldg No 102—
Bldg No 112—
Bldg No 122—
Bldg No 132—
Bldg No 142—
Bldg No 152—
Bldg No 162—
Show all 25 buildingsShow fewer buildings

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 units registered

Parking

BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
Bldg No 1Closed/Covered00000
Bldg No 1Open Space00000
Bldg No 10Closed/Covered00000
Bldg No 10Open Space00000
Bldg No 11Closed/Covered00000
Bldg No 11Open Space00000
Bldg No 12Closed/Covered00000
Bldg No 12Open Space00000
Show all 50 parking rowsShow fewer parking rows
BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
Bldg No 13Closed/Covered00000
Bldg No 13Open Space00000
Bldg No 14Closed/Covered00000
Bldg No 14Open Space00000
Bldg No 15Closed/Covered00000
Bldg No 15Open Space00000
Bldg No 16Closed/Covered00000
Bldg No 16Open Space00000
Bldg No 17Closed/Covered00000
Bldg No 17Open Space00000
Bldg No 18Closed/Covered00000
Bldg No 18Open Space00000
Bldg No 19Closed/Covered00000
Bldg No 19Open Space00000
Bldg No 20Closed/Covered00000
Bldg No 20Open Space00000
Bldg No 22 Wing E 14Closed/Covered00000
Bldg No 22 Wing E 14Open Space00000
Bldg No 23 Wing E13Closed/Covered00000
Bldg No 23 Wing E13Open Space00000
Bldg No 24 Wing E10Closed/Covered00000
Bldg No 24 Wing E10Open Space00000
Bldg No 24 Wing E11Closed/Covered00000
Bldg No 24 Wing E11Open Space00000
Bldg No 24 Wing E 12Closed/Covered00000
Bldg No 24 Wing E 12Open Space00000
Bldg No 3 Wing E2Closed/Covered00000
Bldg No 3 Wing E2Open Space00000
Bldg No 3 Wing E3Closed/Covered00000
Bldg No 3 Wing E3Open Space00000
Bldg No 4Closed/Covered00000
Bldg No 4Open Space00000
Bldg No 5 Wing 15Closed/Covered00000
Bldg No 5 Wing 15Open Space00000
Bldg No 5 Wing 16Closed/Covered00000
Bldg No 5 Wing 16Open Space00000
Bldg No 5 Wing 17Closed/Covered00000
Bldg No 5 Wing 17Open Space00000
Bldg No 8Closed/Covered00000
Bldg No 8Open Space00000
Bldg No 9Closed/Covered00000
Bldg No 9Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Bldg No 1

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Bldg No 10

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Bldg No 11

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Show all 26 buildings and common areasShow fewer buildings and common areas

Bldg No 12

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Bldg No 13

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Bldg No 14

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Bldg No 15

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Bldg No 16

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Bldg No 17

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Bldg No 18

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Bldg No 19

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Bldg No 20

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Bldg No 22 Wing E 14

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Bldg No 23 Wing E13

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Bldg No 24 Wing E10

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Bldg No 24 Wing E11

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Bldg No 24 Wing E 12

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Bldg No 3 Wing E2

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Bldg No 3 Wing E3

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Bldg No 4

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Bldg No 5 Wing 15

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Bldg No 5 Wing 16

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Bldg No 5 Wing 17

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Bldg No 8

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Bldg No 9

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Common areas and amenities

  • Internal Roads & FootpathsBT ROAD100%
  • Water Supply100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)100%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree Planting100%
  • Street Lighting100%
Show all 15 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And Disposal100%
  • Water conservation /Rain water harvestingRain water Harvesting100%
  • Energy managemcntLED LIGHTS INSTALLED100%
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationElectrical Meter Room100%
  • Aggregate area of recreational Open Space100%
  • Open Parking100%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

20 documents held by Deedo, 38 filings listed on MahaRERA's project page

Title report (2)

Encumbrance details (2)

Commencement certificate

Form B

Allotment letter (3)

Show all 58 documentsShow fewer documents

Allotment letter (3)

Registration certificate

Form 5

Extension certificate

Other

Layout plan (4)

Building plan (3)

Document library

  • Proforma of Allotment letterALLOTMENT LETTER.PDF · uploaded 29 Jul 2017View
  • Proforma of Allotment letterTABA PAVTI.PDF · uploaded 29 Jul 2017View
  • Commencement Certificates / NA Order for plotted developmentr-1 commencement certificate_001.pdf · uploaded 29 Jul 2017View
  • Building Plan Approval (IOD)iod plan_opt123.pdf · uploaded 29 Jul 2017View
  • Details of encumbrancesnon encubarance certificate.pdf · uploaded 29 Jul 2017View
  • Copy of the legal title reportland clearance.pdf · uploaded 29 Jul 2017View
  • Copy of Layout Approval (in case of layout)iod plan_opt123.pdf · uploaded 29 Jul 2017View
  • Declaration in FORM Bform b0001_opt.pdf · uploaded 29 Jul 2017View
  • Copy of the legal title report01-08-2017.pdf · uploaded 1 Aug 2017View
  • Proforma of Allotment letterOFFER LETTER.PDF · uploaded 23 Aug 2017View
  • Certificates of CA (Form 5)form 5 jalna_opt.pdf · uploaded 13 Jun 2019View
  • a Details of encumbrances concerned to FinanceRERA.pdf · uploaded 7 Dec 2023View
  • b Details of encumbrances concerned to LegalRERA.pdf · uploaded 7 Dec 2023View
  • Declaration about Commencement CertificateRERA.pdf · uploaded 7 Dec 2023View
  • CERSAI detailsRERA.pdf · uploaded 7 Dec 2023View
  • Disclosure of Interest in Other Real Estate OrganizationsRERA.pdf · uploaded 7 Dec 2023View
  • Proforma of Agreement for saleRERA.pdf · uploaded 7 Dec 2023View
  • Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameRERA.pdf · uploaded 7 Dec 2023View
  • Deviation Report with respect to Allotment letterRERA.pdf · uploaded 7 Dec 2023View
  • Deviation Report with respect to model copy of AgreementRERA.pdf · uploaded 7 Dec 2023View
  • Copy of Layout Approval (in case of layout)LAYOUT_compressed.pdf · uploaded 28 Nov 2024View
  • Building Plan Approval (IOD)BUILDING LAYOUT_compressed.pdf · uploaded 28 Nov 2024View
  • Copy of Layout Approval (in case of layout)20250109_134347_compressed.pdf · uploaded 9 Jan 2025View
  • Building Plan Approval (IOD)BUILDING PLAN 33_compressed.pdf · uploaded 9 Jan 2025View
  • Copy of Layout Approval (in case of layout)33(2017)LAYOUT_compressed (1).pdf · uploaded 14 Jan 2025View
  • Building Plan Approval (IOD)33(2017) BUILDING PLAN_compressed.pdf · uploaded 14 Jan 2025View

Promoter documents

  • Legal Title reportland clearance.pdf · uploaded 29 Jul 2017View
  • Declaration Form Bform b0001_opt.pdf · uploaded 29 Jul 2017View
  • Legal Title report01-08-2017.pdf · uploaded 1 Aug 2017View

Technical documents

  • Building Plan Approvaliod plan_opt123.pdfView
  • Layout Approvaliod plan_opt123.pdfView
  • Layout Approval20250109_134347_compressed.pdfView
  • Layout Approval33(2017)LAYOUT_compressed (1).pdfView
  • Layout ApprovalLAYOUT_compressed.pdfView
  • Building Plan ApprovalBUILDING PLAN 33_compressed.pdfView
  • Building Plan Approval33(2017) BUILDING PLAN_compressed.pdfView
  • Building Plan ApprovalBUILDING LAYOUT_compressed.pdfView

Proforma allotment letter

  • Proforma allotment letterTABA PAVTI.PDFView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Jalna (M Cl), Jalna taluka

Survey, CTS, gat or plot numbers

488/15

As published on MahaRERA's project page

488/15

Boundaries

North
S No 488 Mhada Land
South
S No 488 Govt Of Maharashtra Land
East
S No 488 Govt Of Maharashtra Land
West
S No 488 Govt Of Maharashtra Land

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectGirdhari Shah & Associates—
ArchitectGirdhari Shah & Associates—
ArchitectGirdhari Shah & Associates—
ArchitectGirdhari Shah & Associates—
ArchitectGirdhari Shah & Associates—
ArchitectGirdhari Shah & Associates—
ArchitectGirdhari Shah & Associates—
ArchitectGirdhari Shah & Associates—
Show all 64 professionalsShow fewer professionals
RoleNameRegistration no.
ArchitectGirdhari Shah & Associates—
ArchitectGirdhari Shah & Associates—
ArchitectGirdhari Shah & Associates—
ArchitectGirdhari Shah & Associates—
ArchitectGirdhari Shah & Associates—
ArchitectGirdhari Shah & Associates—
ArchitectGirdhari Shah & Associates—
ArchitectGirdhari Shah & Associates—
Chartered accountantChief Account Officer Mhada Aurangabad—
Chartered accountantChief Account Officer Mhada Aurangabad—
Chartered accountantChief Account Officer Mhada Aurangabad—
Chartered accountantChief Account Officer Mhada Aurangabad—
Chartered accountantChief Account Officer Mhada Aurangabad—
Chartered accountantChief Account Officer Mhada Aurangabad—
Chartered accountantChief Account Officer Mhada Aurangabad—
Chartered accountantChief Account Officer Mhada Aurangabad—
Chartered accountantChief Account Officer Mhada Aurangabad—
Chartered accountantChief Account Officer Mhada Aurangabad—
Chartered accountantChief Account Officer Mhada Aurangabad—
Chartered accountantChief Account Officer Mhada Aurangabad—
Chartered accountantChief Account Officer Mhada Aurangabad—
Chartered accountantChief Account Officer Mhada Aurangabad—
Chartered accountantChief Account Officer Mhada Aurangabad—
Chartered accountantChief Account Officer Mhada Aurangabad—
EngineerSwapnil S Takane—
EngineerSwapnil S Takane—
EngineerSwapnil S Takane—
EngineerSwapnil S Takane—
EngineerSwapnil S Takane—
EngineerSwapnil S Takane—
EngineerSwapnil S Takane—
EngineerSwapnil S Takane—
EngineerSwapnil S Takane—
EngineerSwapnil S Takane—
EngineerSwapnil S Takane—
EngineerSwapnil S Takane—
EngineerSwapnil S Takane—
EngineerSwapnil S Takane—
EngineerSwapnil S Takane—
EngineerSwapnil S Takane—
OtherWonder Construction—
OtherWonder Construction—
OtherWonder Construction—
OtherWonder Construction—
OtherWonder Construction—
OtherWonder Construction—
OtherWonder Construction—
OtherWonder Construction—
OtherWonder Construction—
OtherWonder Construction—
OtherWonder Construction—
OtherWonder Construction—
OtherWonder Construction—
OtherWonder Construction—
OtherWonder Construction—
OtherWonder Construction—

Source: MahaRERA project page. Contact details are not shown.

Data through10 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology