Zire Rushi Construction
Company or firm · 2 projects · 2 MahaRERA registrations
2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date1 of 1 past their proposed date, not extended
+2 moMedian delayvs RERA proposed date · 1 extended
1Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| The KollageP51800012084 | Andheri | 2017 | Certificate Signed | 15 Aug 2026 | 15 Aug 2026 | On date |
| KyronPC1180002600583 | Gundavali | 2026 | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 4 months, for Kyron (PC1180002600583).
Regulatory cases across projects
- Regulatory orderRegulatory order: PROJECT NAME:THE KOLLAGE (Regulatory Case No. 195 OF 2024) dated 30 May 2024. · The Kollage · P51800012084 · 30 May 2024
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology