Company or firm · 5 projects · 5 MahaRERA registrations

Projects55 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date75%3 of 4 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Zee SquareP51800003888Andheri2017Not reported30 Dec 201930 Dec 2021+24 months
Zee TulsiP51800004559Andheri2017Not reported31 Dec 2026—On date
Zee UshaP51800005143Andheri2017Not reported30 Sep 2020—On date
Zee SahyadriP51800006241Andheri2017Not reported30 Dec 2023—On date
Zee ChahyaP51800007998Andheri2017Not reported30 Sep 2020—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Zee Square+24 mo
  • Zee TulsiOn date
  • Zee UshaOn date
  • Zee SahyadriOn date
  • Zee ChahyaOn date

Track record notes

  • 3 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 24 months, for Zee Square (P51800003888).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology