Yogiraj Skyline
Company or firm · 3 projects · 3 MahaRERA registrations
3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Shivleela Co. Op. Hsg. Society. Ltd.P51700055226 | Dombivli | 2024 | Active | 31 Dec 2026 | — | On date |
| Kubber ZenitthPR1330002501202 | Dombivli | 2025 | Not reported | 25 Feb 2028 | — | On date |
| Nilesh Co-OP Housing Society LtdPR1330002601276 | Chole | 2026 | Not reported | 27 Dec 2028 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology