Yogeshwar Realty

Company or firm · 7 projects · 7 MahaRERA registrations · 2 reported completed

7Projects7 RERA registrations
2Completedas reported on MahaRERA project pages
100%Kept RERA date6 of 6 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Shivalik SkyP51600014843Nashik2018Completed30 Dec 2023—On date
Shivalik SankalpP51600020755Nashik2019Certificate Signed30 Dec 202530 Dec 2025On date
Shivalik SigmaP51600021505Nashik2019Completed30 Dec 2025—On date
Shivalik Sparsh 2P51600022262Nashik2019Certificate Signed30 Dec 202530 Dec 2025On date
Shivalik SkyparkP51600025573Nashik2020Certificate Signed30 Sep 202630 Sep 2026On date
Shivalik SiddhiP51600028479Nashik2021Certificate Signed30 Sep 202630 Sep 2026On date
Shivalik SkygreenP51600033085Nashik2022Certificate Signed31 Dec 202630 Apr 2027+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Shivalik SkyOn date
  • Shivalik SankalpOn date
  • Shivalik SigmaOn date
  • Shivalik Sparsh 2On date
  • Shivalik SkyparkOn date
  • Shivalik SiddhiOn date
  • Shivalik Skygreen+4 mo

Track record notes

  • 6 of 6 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 4 months, for Shivalik Skygreen (P51600033085).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology