Yogesh Kailas Harak

Individual promoter · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 1 past their proposed date, not extended
+8 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sai Srushti Phase IIP51600046530Nashik2022Certificate Signed31 Dec 202431 Dec 2025+12 months
Shivshambho Heights Co op Hsg Soc LtdP51600077592Nashik2024Certificate Signed30 Apr 202730 Aug 2027+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sai Srushti Phase II+12 mo
  • Shivshambho Heights Co op Hsg Soc Ltd+4 mo

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 12 months, for Sai Srushti Phase II (P51600046530).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology