Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date50%1 of 2 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Park Land - 1 - iP52100002945Pune (M Corp.)2017Not reported30 Dec 201929 Dec 2021+24 months
Parkland - I C buildingP52100020792Haveli2019Not reported30 Mar 2024—On date
Parkland 1 D BuildingP52100079835Haveli2025Not reported30 Sep 2029—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Park Land - 1 - i+24 mo
  • Parkland - I C buildingOn date
  • Parkland 1 D BuildingOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 24 months, for Park Land - 1 - i (P52100002945).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology