Yashraj Infrastructure
Company or firm · 4 projects · 4 MahaRERA registrations
Projects44 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%3 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Tejal SanskrutiP51500007020 | Aurangabad (M Corp.) | 2017 | Not reported | 22 Jan 2018 | — | On date |
| Yashraj Garden Phase 1P51500015997 | Aurangabad | 2018 | Not reported | 30 Sep 2020 | — | On date |
| Yash Shiv ShradhhaP51500033234 | Aurangabad | 2022 | Not reported | 31 Dec 2024 | — | On date |
| Yashraj Dream CityP51500054526 | Ashrafpur | 2024 | Not reported | 31 Dec 2027 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology