Yashraj Corporation

Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 3 past their proposed date, not extended
Median delay+34 movs RERA proposed date · 3 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Moreshwar towerP51800003786Kurla2017Not reported15 Aug 201830 Jun 2022+46 months
Devdatta TowerP51800004163Kurla2017Not reported30 Nov 202030 Sep 2023+34 months
Shiv Chandra Sra ChsP51800010916Kurla2017Not reported30 Jun 202131 Dec 2023+30 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Moreshwar tower+46 mo
  • Devdatta Tower+34 mo
  • Shiv Chandra Sra Chs+30 mo

Track record notes

  • 0 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 46 months, for Moreshwar tower (P51800003786).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology