Yash Infra

Company or firm · 4 projects · 4 MahaRERA registrations

Projects44 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date75%3 of 4 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Nalanda ChsP51700007972Thane (M Corp.)2017Not reported28 Feb 2021—On date
Shilpa ChsP51700009903Thane (M Corp.)2017Not reported29 Dec 2020—On date
Ramleela Co-operative Housing Society LimitedP51700015143Thane (M Corp.)2018Not reported18 Dec 202131 Mar 2026+51 months
Satyaneelayam Co Op HSg SocietyP51700049465Thane (M Corp.)2023Not reported31 Dec 2025—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Nalanda ChsOn date
  • Shilpa ChsOn date
  • Ramleela Co-operative Housing Society Limited+51 mo
  • Satyaneelayam Co Op HSg SocietyOn date

Track record notes

  • 3 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 51 months, for Ramleela Co-operative Housing Society Limited (P51700015143).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology