Westin Sankalp Developers

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Radhakrishna Chs LtdP51800018207Borivali2018Not reported30 Dec 2022—On date
Rajan Dinakar Phatak And OthersP51800028236Borivali2021Not reported30 Jun 2024—On date
Deepali Darshan J. P. Nagar Co-Operative Housing Society LimitedP51800077319Eksar Pahadi2024Certificate Signed31 Dec 202630 Apr 2027+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Radhakrishna Chs LtdOn date
  • Rajan Dinakar Phatak And OthersOn date
  • Deepali Darshan J. P. Nagar Co-Operative Housing Society Limited+4 mo

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 4 months, for Deepali Darshan J. P. Nagar Co-Operative Housing Society Limited (P51800077319).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology