Company or firm · 9 projects · 9 MahaRERA registrations
Also appears as VYAS BUILDCON PVT. LTD. · Vyas Buildcon Private Limited · Vyas Buildcon Pvt Ltd
9Projects9 RERA registrations
0Completedas reported on MahaRERA project pages
71%Kept RERA date5 of 7 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 4 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Pratibha Sadan Co. Op. Hsg. Soc.P52100002624 | Kothrud | 2017 | Certificate Signed | 31 Mar 2018 | 31 Mar 2019 | +12 months |
| Aishwarya ResidencyP52100002455 | Baner | 2017 | Certificate Signed | 31 Dec 2017 | 31 Dec 2018 | +12 months |
| Alankapurishree Co.op.hsg.soc.ltd.P52100018752 | Kothrud | 2018 | Certificate Signed | 30 Jun 2022 | 30 Jun 2022 | On date |
| Aasawari Co. Op. Hsg.societyP52100024235 | Kothrud | 2020 | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| Sudhendu Co Op Hsg SocietyP52100029983 | Kothrud | 2021 | Certificate Signed | 30 Apr 2024 | 30 Apr 2024 | On date |
| 31 Ideal Co Op Hsg SocP52100047442 | Haveli | 2022 | Certificate Signed | 30 Jul 2025 | 30 Jul 2025 | On date |
| Swapnali Co Op Hsg SocP52100049943 | Kothrud | 2023 | Certificate Signed | 3 Jun 2025 | 3 Jun 2025 | On date |
| Anudatta CHSP52100079237 | Pune (M Corp.) | 2025 | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 months |
| Purti Apartments CondominiumPR1260002501388 | Erandwana North | 2025 | Certificate Signed | 1 Jun 2028 | 1 Oct 2028 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 5 of 7 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 12 months, for Pratibha Sadan Co. Op. Hsg. Soc. (P52100002624).
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 4 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.