Skip to content
Deedo home
Menu

Vr Constructions

Company or firm · 1 project · 1 MahaRERA registration

1Projects1 RERA registration
0Completedas reported on MahaRERA project pages
100%Kept RERA date1 of 1 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
1Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Shree Sai ResidencyP50500049243Nagpur (M Corp.)2023Not reported31 Dec 2025—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Shree Sai ResidencyOn date

Track record notes

  • 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology