Viva Swastik Homes

Company or firm · 3 projects · 4 MahaRERA registrations

Projects34 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 1 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Gulmohar HeritageP99000002070Vasaivirar City (M Corp)2017Not reported31 Dec 201731 May 2019+17 months
Gulmohar HeritageP99000028156Vasaivirar City (M Corp)2021Not reported31 May 2027—On date
Parijat Heights Building No 3 Wing AP99000028594Vasai Virar City (M Corp)2021Not reported31 May 2027—On date
Gulmohar Heritage Building No 3 Wing E Phase llP99000033324Vasaivirar City (M Corp)2022Not reported31 Dec 2026—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Gulmohar Heritage+17 mo
  • Gulmohar HeritageOn date
  • Parijat Heights Building No 3 Wing AOn date
  • Gulmohar Heritage Building No 3 Wing E Phase llOn date

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 17 months, for Gulmohar Heritage (P99000002070).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology