Viva Homes Private Limited

Company or firm · 12 projects · 12 MahaRERA registrations

12Projects12 RERA registrations
0Completedas reported on MahaRERA project pages
10%Kept RERA date1 of 10 past their proposed date, not extended
+54 moMedian delayvs RERA proposed date · 10 extended
1Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Viva Vishnupuram - AmogP99000002954Palghar2017Certificate Signed30 Jun 202130 Dec 2025+54 months
Viva Mhatre MansionP51900003443Ward Gnorth2017Certificate Signed31 Dec 201931 Dec 2024+60 months
Viva Vishnupuram -AnantP99000003346Palghar2017Certificate Signed30 Jun 202130 Dec 2025+54 months
Viva Vishnupuram - AnaghaP99000005508Palghar2017Certificate Signed30 Jun 202130 Dec 2025+54 months
Viva Vishnupuram - AnandP99000005718Palghar2017Certificate Signed30 Jun 202130 Dec 2025+54 months
Viva Vishnupuram- AmrutP99000007044Palghar2017Certificate Signed30 Jun 202130 Dec 2025+54 months
Viva Vishnupuram -AdityaP99000007089Palghar2017Certificate Signed30 Jun 202130 Dec 2025+54 months
Viva Vishnupuram -ArchitP99000007726Palghar2017Certificate Signed30 Jun 202130 Dec 2025+54 months
Viva SwaranganP99000008546Palghar2017Certificate Signed30 Dec 202630 Apr 2027+4 months
Royal AccordP51800010302Borivali2017Certificate Signed30 Jun 202730 Jun 2027On date
Viva Vedanta - Bldg No. 2P99000007076Vasaivirar City (M Corp)2017Certificate Signed31 Dec 201731 Dec 2017On date
Viva Vedanta Bldg 1P99000016520Vasaivirar City (M Corp)2018Certificate Signed30 Dec 202214 Dec 2023+12 months
Show all 12 registrationsShow fewer

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Viva Vishnupuram - Amog+54 mo
  • Viva Mhatre Mansion+60 mo
  • Viva Vishnupuram -Anant+54 mo
  • Viva Vishnupuram - Anagha+54 mo
  • Viva Vishnupuram - Anand+54 mo
  • Viva Vishnupuram- Amrut+54 mo
  • Viva Vishnupuram -Aditya+54 mo
  • Viva Vishnupuram -Archit+54 mo
  • Viva Swarangan+4 mo
  • Royal AccordOn date
Show all 12 registrations
  • Viva Vedanta - Bldg No. 2On date
  • Viva Vedanta Bldg 1+12 mo

Track record notes

  • 1 of 10 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 60 months, for Viva Mhatre Mansion (P51900003443).

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology