Vision Ace Aop
Company or firm · 3 projects · 3 MahaRERA registrations
Also appears as M/S. Vision Ace Aop · VISION ACE
Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date67%2 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Vision Ace Phase 1P52100017748 | Tathwade | 2018 | Not reported | 30 Oct 2023 | — | On date |
| Vision Ace Phase IIP52100022545 | Tathwade | 2019 | Not reported | 30 Oct 2024 | — | On date |
| Vision Ace MHADAP52100026135 | Tathwade | 2020 | Not reported | 30 Oct 2022 | 30 Oct 2023 | +12 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 12 months, for Vision Ace MHADA (P52100026135).
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 3 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology