Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 1 past their proposed date, not extended
+22 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Vishnu Vatika Wing A And B Phase IP51700009860Badlapur (M Cl)2017Certificate Signed31 Oct 201931 May 2023+43 months
Vishnu Vatika Wing C Phase IIP51700020130Badlapur (M Cl)2019Certificate Signed31 Dec 202631 Dec 2026On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Vishnu Vatika Wing A And B Phase I+43 mo
  • Vishnu Vatika Wing C Phase IIOn date

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 43 months, for Vishnu Vatika Wing A And B Phase I (P51700009860).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.