Vishal Sanjay Galande

Individual promoter · 1 project · 1 MahaRERA registration

Projects11 RERA registration
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 1 past their proposed date, not extended
Median delay+13 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
The CosmopolisP52100001149Hadapsar2017Not reported15 Sep 201930 Oct 2020+13 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • The Cosmopolis+13 mo

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 13 months, for The Cosmopolis (P52100001149).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology