Company or firm · 3 projects · 4 MahaRERA registrations

Projects34 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%1 of 1 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
OjasP53100049665Sangli Miraj Kupwad (M Corp.)2023Not reported30 Jun 2025—On date
OjasP53100078498Sangli Miraj Kupwad (M Corp.)2024Not reported30 May 2027—On date
Shubha VastuPR1290002501907Sangli Miraj Kupwad (M Corp.)2025Not reported31 Dec 2028—On date
Park ViewPR1290002501966Sangli Miraj Kupwad (M Corp.)2026Not reported30 Aug 2028—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • OjasOn date
  • OjasOn date
  • Shubha VastuOn date
  • Park ViewOn date

Track record notes

  • 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology