Vinay Maganlal Karnavat
Individual promoter · 4 projects · 4 MahaRERA registrations
4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date3 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Sai Laxmi VillasP51600016097 | Nashik Road | 2018 | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
| Rajgadh Co-Op Housing Society LtdP51600028054 | Nashik Road | 2021 | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| Shree Bhagwati Co-Op Hsg SocietyP51600047578 | Deolaligaon | 2022 | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | On date |
| Shantiprasad Co-Op Housing SocietyP51600052466 | Nashik Road | 2023 | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology