Vilas Javdekar Eco Shelters Private Limited

Company or firm · 8 projects · 9 MahaRERA registrations

Projects89 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%9 of 9 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Yashwin HinjawadiP52100000037Man2017Not reported30 Jun 2025—On date
Prudentia - Phase 1P52100000114Wakad2017Not reported30 Jun 2019—On date
YashONE HinjawadiP52100019468Man2019Not reported30 Dec 2023—On date
YashONE Wakad CentralP52100020910Wakad2019Not reported30 Dec 2024—On date
YashONE HinjawadiP52100024108Man2020Not reported30 Mar 2025—On date
VJ One AvenueP52100025592Man2020Not reported30 Dec 2023—On date
VJ Grand CentralP52100026304Wakad2020Not reported30 Dec 2024—On date
Yashwin SuperNovaP52100028652Wakad2021Not reported30 Mar 2026—On date
VJ Town CentreP52100028755Wakad2021Not reported30 Sep 2024—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Yashwin HinjawadiOn date
  • Prudentia - Phase 1On date
  • YashONE HinjawadiOn date
  • YashONE Wakad CentralOn date
  • YashONE HinjawadiOn date
  • VJ One AvenueOn date
  • VJ Grand CentralOn date
  • Yashwin SuperNovaOn date
  • VJ Town CentreOn date

Track record notes

  • 9 of 9 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology