Vikrant Vikas Raikar

Individual promoter · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+3 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Simran MajesticP52000002117Taloje Majkur2017Not reported30 Jun 201831 Dec 2018+6 months
Yashraj HeightsP51700034878Navi Mumbai (M Corp.)2022Not reported31 Jan 2025—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Simran Majestic+6 mo
  • Yashraj HeightsOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 6 months, for Simran Majestic (P52000002117).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology