Vikram Vedprakash Agarwal
Individual promoter · 5 projects · 5 MahaRERA registrations
5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
75%Kept RERA date3 of 4 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| NatrajplazaP52100015876 | Pune (M Corp.) | 2018 | Certificate Signed | 30 Sep 2020 | 25 Mar 2022 | +18 months |
| Shree Siddhivinayak ResidencyP52100021926 | Pune (M Corp.) | 2019 | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| NatrajKamalP52100031503 | Haveli | 2021 | Certificate Signed | 30 Nov 2024 | 30 Nov 2024 | On date |
| Vardhaman VillaP52100050584 | Pune (M Corp.) | 2023 | Certificate Signed | 31 Oct 2024 | 31 Oct 2024 | On date |
| Natraj ResidencyP52100076714 | Pune (M Corp.) | 2024 | Certificate Signed | 30 Apr 2028 | 30 Apr 2028 | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 3 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 18 months, for Natrajplaza (P52100015876).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology