Vikas Narayan Raikar
Individual promoter · 4 projects · 4 MahaRERA registrations
Also appears as Vikas Construction Co
4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+13 moMedian delayvs RERA proposed date · 4 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Sagar ApartmentP51800002093 | Kurla | 2017 | Not reported | 20 Mar 2019 | 21 Dec 2020 | +21 months |
| Simran HeightsP51800002238 | Kurla | 2017 | Not reported | 24 Sep 2019 | 31 Mar 2025 | +66 months |
| Kurla Vijay Rahivashi Sangh Co-op. Hsg.Soc.Ltd.P51800055918 | Chembur | 2024 | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 months |
| Yash ResidencyPM1180002600628 | Chembur | 2026 | Certificate Signed | 31 Jan 2030 | 31 May 2030 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 66 months, for Simran Heights (P51800002238).
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology