Vijay Prabhakarrao Naidu

Individual promoter · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Prateek Naidu Industrial ParkP50500015828Nildoh2018Certificate Signed5 Jan 202331 May 2025+28 months
Prateek Naidu Residential ParkP50500034446Nildoh2022Certificate Signed5 Apr 20255 Apr 2025On date
Prateek Naidu Industrial Park 2PP1190002600342Waddhamna2026Not reported31 Mar 2033—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Prateek Naidu Industrial Park+28 mo
  • Prateek Naidu Residential ParkOn date
  • Prateek Naidu Industrial Park 2On date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 28 months, for Prateek Naidu Industrial Park (P50500015828).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology