Vijay Prabhakarrao Naidu
Individual promoter · 3 projects · 3 MahaRERA registrations
3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Prateek Naidu Industrial ParkP50500015828 | Nildoh | 2018 | Certificate Signed | 5 Jan 2023 | 31 May 2025 | +28 months |
| Prateek Naidu Residential ParkP50500034446 | Nildoh | 2022 | Certificate Signed | 5 Apr 2025 | 5 Apr 2025 | On date |
| Prateek Naidu Industrial Park 2PP1190002600342 | Waddhamna | 2026 | Not reported | 31 Mar 2033 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 28 months, for Prateek Naidu Industrial Park (P50500015828).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology