Vijay Construction & Developers

Company or firm · 2 projects · 2 MahaRERA registrations · 1 reported completed

2Projects2 RERA registrations
1Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Siddhivinayak AppartmentP50500001612Beltarodi2017Completed31 Aug 2019—On date
Parijat EnclaveP50500046378Besa2022Certificate Signed31 Aug 202431 Aug 2024On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Siddhivinayak AppartmentOn date
  • Parijat EnclaveOn date

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.