Company or firm · 3 projects · 4 MahaRERA registrations

3Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date2 of 4 past their proposed date, not extended
+6 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Vertical Oriana Phase IIP52100003699Keshavnagarmundwa2017Certificate Signed30 Jun 201930 Jun 2019On date
Vertical Oriana Phase IP52100003700Keshavnagar Mundwa2017Certificate Signed31 Dec 201831 Dec 2018On date
Vertical OrianaP52100005269Keshavnagar Mundwa2017Certificate Signed31 Jan 202130 Dec 2021+11 months
Vertical OrianaP52100021565Keshavnagar Mundwa2019Certificate Signed30 Sep 202231 Dec 2026+51 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Vertical Oriana Phase IIOn date
  • Vertical Oriana Phase IOn date
  • Vertical Oriana+11 mo
  • Vertical Oriana+51 mo

Track record notes

  • 2 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 51 months, for Vertical Oriana (P52100021565).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology