Company or firm · 4 projects · 4 MahaRERA registrations

4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+4 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Veer VishwaP51700054017Thane (M Corp.)2023Certificate Signed20 Feb 202720 Jun 2027+4 months
Veer HeightsP51700076668Thane (M Corp.)2024Active30 Apr 2028—On date
Veer EnclaveP51700078859Thane (M Corp.)2025Certificate Signed14 Jun 202814 Oct 2028+4 months
Veer SapphireP51700079992Thane (M Corp.)2025Certificate Signed25 Sep 202925 Jan 2030+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Veer Vishwa+4 mo
  • Veer HeightsOn date
  • Veer Enclave+4 mo
  • Veer Sapphire+4 mo

Track record notes

  • Longest extension on record: 4 months, for Veer Vishwa (P51700054017).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology