Veena Developers

Company or firm · 5 projects · 5 MahaRERA registrations

Projects55 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%2 of 2 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Veena Santoor Phase IIP51800001482Borivali2017Not reported31 Dec 2019—On date
Veena SignatureP51800002804Borivali2017Not reported31 Dec 2019—On date
Veena Samrajya-Sector-VIIIP99000021726Mahim2019Not reported31 Mar 2027—On date
Veena SynergyP51800049356Andheri2023Not reported31 Dec 2026—On date
Veena SuyogP51800050707Borivali2023Not reported31 Dec 2026—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Veena Santoor Phase IIOn date
  • Veena SignatureOn date
  • Veena Samrajya-Sector-VIIIOn date
  • Veena SynergyOn date
  • Veena SuyogOn date

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology