Vasukamal & Associates

Company or firm · 1 project · 1 MahaRERA registration · 1 reported completed

1Projects1 RERA registration
1Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 1 past their proposed date, not extended
+13 moMedian delayvs RERA proposed date · 1 extended
1Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Vasukamal SamruddhiP49900000069Jalgaon (M Corp.)2017Completed31 Dec 201831 Jan 2020+13 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Vasukamal Samruddhi+13 mo

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 13 months, for Vasukamal Samruddhi (P49900000069).

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology