Vastu Shilpa Complex Designers Pvt Ltd

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+18 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
SMGK ASSOCIATE RESIDENCY Wing B Phase 2 17th to 20th FloorsP51800004663Andheri2017Certificate Signed31 Dec 201930 Dec 2022+36 months
SMGK ASSOCIATE RESIDENCY Wing B Phase 1 -1st to 16th floorsP51800008954Andheri2017Certificate Signed31 Dec 201831 Dec 2018On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • SMGK ASSOCIATE RESIDENCY Wing B Phase 2 17th to 20th Floors+36 mo
  • SMGK ASSOCIATE RESIDENCY Wing B Phase 1 -1st to 16th floorsOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 36 months, for SMGK ASSOCIATE RESIDENCY Wing B Phase 2 17th to 20th Floors (P51800004663).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology