Vastu Darshan Developers Llp
Company or firm · 3 projects · 3 MahaRERA registrations · 1 reported completed
3Projects3 RERA registrations
1Completedas reported on MahaRERA project pages
33%Kept RERA date1 of 3 past their proposed date, not extended
+16 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Durga Smruti Chs LtdP51800020670 | Borivali | 2019 | Completed | 30 Apr 2022 | — | On date |
| Acharya Ashram Sahakari Griha Rachana Sanstha MaryaditP51800027379 | Borivali | 2020 | Not reported | 30 Oct 2023 | 31 Mar 2026 | +29 months |
| Darshan HeightsP51800030456 | Borivali | 2021 | Not reported | 31 Dec 2023 | 21 Apr 2025 | +16 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 29 months, for Acharya Ashram Sahakari Griha Rachana Sanstha Maryadit (P51800027379).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology