Vastav Developers Pvt Ltd
Company or firm · 3 projects · 3 MahaRERA registrations
Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 2 past their proposed date, not extended
Median delay+21 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Awantika Chs LtdP51800002710 | Kurla | 2017 | Not reported | 30 Jun 2021 | 31 Dec 2024 | +42 months |
| MeghmanishaP51800018919 | Kurla | 2018 | Not reported | 30 Oct 2022 | 31 Jul 2024 | +21 months |
| Eknath GruhP51800077854 | Borivali | 2024 | Not reported | 31 Oct 2026 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 42 months, for Awantika Chs Ltd (P51800002710).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology