Vasanta Shivramji Dangare

Individual promoter · 6 projects · 6 MahaRERA registrations

Projects66 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date50%2 of 4 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
ShivkashipuramP50500023643Umred (M Cl)2019Not reported30 Dec 2021—On date
Paradise CityP50500028526Umred (M Cl)2021Not reported30 Jun 2022—On date
Shivkashipuram KuhiP50500032900Kuhi2022Not reported31 Dec 202231 Dec 2025+36 months
Kasabai NagariP50500034515Umred (M Cl)2022Not reported31 Mar 202330 Mar 2024+12 months
Chatrapati Shivaji NagarP50500053473Boribhatari (Ri)2023Not reported31 Dec 2028—On date
Chatrapati Shivaji Nagar 2PP1190002601578Umred (M Cl)2026Not reported31 Dec 2031—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • ShivkashipuramOn date
  • Paradise CityOn date
  • Shivkashipuram Kuhi+36 mo
  • Kasabai Nagari+12 mo
  • Chatrapati Shivaji NagarOn date
  • Chatrapati Shivaji Nagar 2On date

Track record notes

  • 2 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 36 months, for Shivkashipuram Kuhi (P50500032900).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology