Skip to content

Vaishnav Constructions

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date1 of 1 past their proposed date, not extended
+2 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
BALAJI SerenityP51600045955Nashik2022Certificate Signed31 Dec 202531 Dec 2025On date
MuktanganP51600053296Nashik2023Certificate Signed31 Dec 202730 Apr 2028+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • BALAJI SerenityOn date
  • Muktangan+4 mo

Track record notes

  • 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 4 months, for Muktangan (P51600053296).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology