Vaichal Constructions Pvt Ltd

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
KalpaVruksha BP52100004001Kasar Amboli2017Certificate Signed31 Dec 201831 Dec 2019+12 months
KalpaVruksha CP52100019364Kasar Amboli2019Certificate Signed30 Dec 202330 Dec 2023On date
Kalpavruksha AP52100077603Kasar Amboli2024Certificate Signed31 Dec 202730 Apr 2028+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • KalpaVruksha B+12 mo
  • KalpaVruksha COn date
  • Kalpavruksha A+4 mo

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 12 months, for KalpaVruksha B (P52100004001).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology