Vagad Constructions

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+38 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Akshar ElitaP51700005621Navi Mumbai (M Corp.)2017Certificate Signed31 Dec 20194 Apr 2025+64 months
Akshar EdeaniaP52000006744Bokadvira2017Certificate Signed31 Dec 201831 Dec 2019+12 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Akshar Elita+64 mo
  • Akshar Edeania+12 mo

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 64 months, for Akshar Elita (P51700005621).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology