Vaastu Triaa Lifespaces LLP

Company or firm · 1 project · 1 MahaRERA registration

1Projects1 RERA registration
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Triaa Galaxy - Phase 1P52100047169Hinjavadi (Ct)2022Certificate Signed30 Jun 202730 Jun 2027On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Triaa Galaxy - Phase 1On date

Track record notes

  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology