Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date1 of 1 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
1Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
SKY GardensP50300023111Amravati (M Corp.)2019Certificate Signed30 Mar 202530 Mar 2025On date
Sky Garden HillsP50300055399Amravati (M Corp.)2024Active31 Dec 2027—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • SKY GardensOn date
  • Sky Garden HillsOn date

Track record notes

  • 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology