Urban Life Realty LLP
Company or firm · 1 project · 1 MahaRERA registration
1Projects1 RERA registration
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+4 moMedian delayvs RERA proposed date · 1 extended
1Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Rakshak Vatika A B C wingsP52100000381 | Sate | 2017 | Certificate Signed | 30 Jun 2027 | 30 Oct 2027 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- Longest extension on record: 4 months, for Rakshak Vatika A B C wings (P52100000381).
Regulatory cases across projects
- Suo motu orderSuo motu order: Secretary, MahaRERA Versus Dreams Construction Pvt Ltd. (Suo Motu Case No. 141 of 2020) dated 27 Feb 2020 · Rakshak Vatika A B C wings · P52100000381 · 6 Mar 2020
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology