Unnathi Estates
Company or firm · 7 projects · 7 MahaRERA registrations
Projects77 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%5 of 5 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases1MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Unnathi Woods Phase VII AP51700000002 | Thane (M Corp.) | 2017 | Not reported | 30 Dec 2025 | — | On date |
| Unnathi Woods Phase III - C1P51700003359 | Thane (M Corp.) | 2017 | Not reported | 31 Dec 2018 | — | On date |
| Unnathi Woods Phase VI - F2P51700004330 | Thane (M Corp.) | 2017 | Not reported | 31 Dec 2018 | — | On date |
| Raunak ResidencyP51700009540 | Thane (M Corp.) | 2017 | Not reported | 31 Dec 2025 | — | On date |
| Unnathi Woods Phase VII-BP51700015800 | Thane (M Corp.) | 2018 | Not reported | 30 Jun 2024 | — | On date |
| Unnathi Woods Phase VI-F1P51700015804 | Thane (M Corp.) | 2018 | Not reported | 30 Dec 2027 | — | On date |
| Unnathi Woods Phase VIIIP51700020921 | Thane | — | Not reported | — | 31 Dec 2027 | — |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 5 of 5 registrations whose RERA proposed completion date has passed were never extended beyond it.
- 1 registration without certificate dates yet; it is left out of the delivery numbers.
Regulatory cases across projects
- Regulatory orderRegulatory order: PROJECT NAME: UNNATHI WOODS PHASE VIII (Regulatory Case No.128 of 2024) dated 16 January 2024. · Unnathi Woods Phase VIII · P51700020921 · 16 Jan 2024
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology