Company or firm · 1 project · 3 MahaRERA registrations

1Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+4 moMedian delayvs RERA proposed date · 3 extended
1Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Nayan Vastu HeritageP99000034936Makane2022Certificate Signed31 Dec 202730 Apr 2028+4 months
Nayan Vastu HeritageP99000035201Makane2022Certificate Signed31 Dec 202630 Apr 2027+4 months
Nayan Vastu HeritageP99000078272Makane2024Certificate Signed31 Dec 202630 Apr 2027+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Nayan Vastu Heritage+4 mo
  • Nayan Vastu Heritage+4 mo
  • Nayan Vastu Heritage+4 mo

Track record notes

  • Longest extension on record: 4 months, for Nayan Vastu Heritage (P99000034936).

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology