Ujjwala Satish Haware
Individual promoter · 5 projects · 5 MahaRERA registrations · 1 reported completed
5Projects5 RERA registrations
1Completedas reported on MahaRERA project pages
60%Kept RERA date3 of 5 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Grand EdificeP51700006407 | Borivali | 2017 | Certificate Signed | 30 Jun 2021 | 30 Dec 2022 | +18 months |
| Grand HeritageP52100014251 | Wakad | 2017 | Certificate Signed | 31 Jan 2021 | 31 Jan 2021 | On date |
| Green SquareP50300014384 | Mhasala | 2017 | Completed | 31 Jul 2019 | — | On date |
| Haware GraceP52100022058 | Wakad | 2019 | Certificate Signed | 30 Dec 2024 | 30 Dec 2024 | On date |
| Haware AlturaP51800029411 | Kurla | 2021 | Certificate Signed | 30 Apr 2026 | 30 Aug 2026 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 3 of 5 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 18 months, for Grand Edifice (P51700006407).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology