Tycoons Avanti Projects Llp
Company or firm · 4 projects · 5 MahaRERA registrations
4Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date2 of 4 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 3 extended
2Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Tycoons Square Avenue III Tower CP51700004049 | Chikanghar | 2017 | Certificate Signed | 30 Jan 2023 | 30 Jun 2025 | +29 months |
| Tycoons Square AvenueP51700004794 | Chikanghar | 2017 | Certificate Signed | 30 Mar 2023 | 30 Jun 2027 | +51 months |
| Tycoons Square Avenue I Tower DP51700023614 | Chikanghar | 2019 | Certificate Signed | 30 Oct 2025 | 30 Oct 2025 | On date |
| Tycoons Square Avenue I Tower AP51700029986 | Chikanghar | 2021 | Certificate Signed | 30 Jul 2025 | 30 Jul 2025 | On date |
| Tycoons Square AvenueP51700035166 | Chikanghar | 2022 | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 51 months, for Tycoons Square Avenue (P51700004794).
Regulatory cases across projects
- Regulatory orderRegulatory order: PROJECT NAME:TYCOONS SQUARE AVENUE I TOWER B (Regulatory Case No. 192 OF 2024) dated 30 May 2024. · Tycoons Square Avenue · P51700004794 · 30 May 2024
- Regulatory orderRegulatory order: PROJECT NAME: TYCOONS SQUARE AVENUE III TOWER C (Regulatory Case No. 18 of 2023) dated 18 May 2023. · Tycoons Square Avenue III Tower C · P51700004049 · 24 May 2023
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology