Tushar Ramchandra Patil

Individual promoter · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
67%Kept RERA date2 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Daffodil ApartmentP52000018298Vadghar (Ct)2018Certificate Signed31 Dec 201931 Dec 2019On date
Orchid ApartmentP52000019246Vadghar (Ct)2019Certificate Signed30 Sep 202030 Sep 2020On date
Cosmos ApartmentP52000020631Vadghar (Ct)2019Certificate Signed30 Sep 202031 Dec 2025+63 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Daffodil ApartmentOn date
  • Orchid ApartmentOn date
  • Cosmos Apartment+63 mo

Track record notes

  • 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 63 months, for Cosmos Apartment (P52000020631).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology